This year, the Taixing High-tech Zone in Taixing city, Jiangsu province, has been focusing on strengthening tracking progress, coordinating the efforts of different parties, and solving construction difficulties for projects.
At the construction site of the Aneng power engineering project, workers have been ramping up project construction since May.
In the early stages, construction was met with difficulties due to a natural gas pipeline spanning key construction areas and undertaking important gas supply tasks throughout the city.
Due to the high safety risks, large number of departments involved, and strict technical standards for the dismantling and renovation of the pipeline, it was considered a complex engineering task.
In response, the zone held a coordination meeting gathering the responsible company, construction units, project owners, supervision units, and relevant government departments.
It also took proactive moves to strengthen communication and collaboration among various units and manage the safety and technology of the project.
After a month of efforts, the new pipeline was replaced and ventilated, passing strict inspection and ensuring work could move ahead on the project.