Since the start of this year, the Jingjiang Economic and Technological Development Zone, Jiangsu province, has been ramping up efforts to advance project construction, adding strong momentum to regional development.
As of the end of May, the zone has completed fixed assets investment of 474 million yuan ($69.69 million), with a completion rate of 52.7 percent.
The zone's three provincial-level major projects this year have also achieved significant progress.
The new energy ship project of New Times Shipbuilding has been completed. Advanced manufacturing workshops such as the intelligent material processing center and the digital and intelligent block manufacturing workshop have been put into production, improving the production efficiency of the company.

The new energy ship site of New Times Shipbuilding. [Photo/WeChat account: ZGJJKFQ]
The construction permit for the key mooring equipment and integrated engineering project for the large-scale floating body of Yaxing Anchor Chain in the deep sea has been obtained, and the construction of engineering piles in Workshop 1 and Workshop 2 has been basically completed.
The construction permit for the key mooring equipment and integrated engineering project for the large-scale floating body of Asian Star Anchor Chain in deep seas has been obtained, and the construction of engineering piles in Workshop 1 and Workshop 2 is more or less finished.
The green, low-carbon, and smart upgrading and reconstruction project of Yangtze River Port Terminal has obtained an administrative license for transportation, and the pile foundation construction of the intelligent control center, mechanical workshop, and dustproof net area is being carried out on schedule.
The zone adheres to building a full-process project follow-up system that encompasses investment attraction, project construction, and production.
The park has established a special service team to provide proactive services, assist in handling procedures, guide the early stages of projects, coordinate project planning, and help resolve difficult issues that projects may face.
As of this year, the zone has processed and completed construction permits for 10 projects and facilitated the commencement of 13.